Progress: January 20 – January 31, 2020
- Prepped site for installing geopiers to stabilize the soil and create foundational support
- Finished work to relocate gas line
- Re-opened bike path
Up Next: February 1 – February 14, 2020
- Start foundation excavation
- Repave bike path
- Form footings and foundation walls
- Begin installing geopiers