Expansion Updates: December – January

Progress: December 16, 2019 – January 3, 2020

  • Set up a project trailer and office at the far end of the lot for John Lawlor, our project superintendent from Harvey Construction
  • Closed off our cafe door and installed fence around the expansion area
  • Relocated gas line that currently lies within the project area
  • Began removing gravel and pavement from building footprint
  • Took down lamp post in expansion footprint (will reuse later in new parking area)

Up Next: January 6 – January 17, 2020

  • Moving dirt to bring site to sub grade
  • Install ground heater
  • Prep site for installing geopiers to stabilize the soil and create foundational support (set to begin January 16; will take 4 days)