Progress: December 16, 2019 – January 3, 2020
- Set up a project trailer and office at the far end of the lot for John Lawlor, our project superintendent from Harvey Construction
- Closed off our cafe door and installed fence around the expansion area
- Relocated gas line that currently lies within the project area
- Began removing gravel and pavement from building footprint
- Took down lamp post in expansion footprint (will reuse later in new parking area)
Up Next: January 6 – January 17, 2020
- Moving dirt to bring site to sub grade
- Install ground heater
- Prep site for installing geopiers to stabilize the soil and create foundational support (set to begin January 16; will take 4 days)