Progress: January 6 – January 17, 2020
- Installed ground heater
- Moved dirt to bring site to sub grade
- Continued work to relocate gas line (small section of the bike path had to be temporarily closed)
Up Next: January 20 – January 31, 2020
- Prep site for installing geopiers to stabilize the soil and create foundational support (set to begin January 22)
- Start excavating for foundation